Reportage Properties is a private developer founded in Abu Dhabi in 2014, where it keeps its head office. It now…

ABOUT

Reportage Properties Overview

Reportage Properties is a private developer founded in Abu Dhabi in 2014, where it keeps its head office. It now trades as Reportage Group. Aref Al Khouri is chairman and Andrea Nucera is CEO and Managing Director; the group's own releases describe Nucera as an owner and key founder and name Felix Limited as its main shareholder. Its shares are not listed. In Dubai it builds mainly mid-priced townhouses and apartments in Dubailand and Dubai Investment Park, and in October 2026 it made its first launch in Meydan.

The reliability picture is mixed but on record. Reportage has delivered Rukan Tower in Dubailand, the first phase of Rukan Lofts, and Leonardo Residences, Oasis Residence 1 and 2 and Al Raha Lofts in Abu Dhabi. Rukan Tower, though, was due in Q4 2022 and was handed over in August 2024. Sales are company-reported: AED 9.6 billion for 2025, up from about AED 5.7 billion in 2024. We found no independent on-time delivery record, so this page gives dated facts, not a verdict. Status below is as read on 11 November 2026.

Reportage's own pages show Verdana 1 in Dubai Investment Park at 97.19% complete and Verdana 2 at 54.40%, Bianca in Dubailand at 54.5% and Taormina Village at 19.4%. R. Hills, a 902-townhouse community in Dubailand, lists a Q4 2028 handover and construction marked as starting soon. Reportage Village, with 1,767 townhouses, launched in September 2023.

Before reserving any off-plan Reportage unit, confirm the Oqood registration, escrow account, payment schedule and the handover date written into the contract. Contact us to compare specific phases.

USEFUL INFORMATION

Things You Should Know

Reportage Properties was founded in Abu Dhabi in 2014 and is headquartered there. The business now presents itself as Reportage Group, and its website footer still carries the Reportage Properties name. Aref Al Khouri is chairman. Andrea Nucera is CEO and Managing Director, and the group's August 2026 IPS release calls him an owner and key founder. Simona Musso is Executive Director and Giovanni Nucera is International CEO.

The group is privately held. A September 2026 release names Felix Limited as Reportage Group's main shareholder. In the same month Reportage launched The Wadi on Yas Canal in Abu Dhabi through Cosmo Developments, a joint venture with Flag Holding Group that Reportage manages. The developer describes itself as debt-free; as a private company it does not publish audited accounts, so that claim and its sales figures are the company's own.

Its first project was Leonardo Residences in Masdar City, which broke ground in April 2016 and was handed over in 2019. It has since spread from Abu Dhabi into Dubai and abroad. Its website lists 19 countries, including Egypt, Saudi Arabia, Türkiye, Azerbaijan, Morocco, Rwanda, Uganda, Kenya, Albania and France.

  • Type: private developer, headquartered in Abu Dhabi

  • Founded: 2014

  • Leadership: Aref Al Khouri (chairman); Andrea Nucera (CEO and Managing Director)

  • Main shareholder: Felix Limited, according to a September 2026 group release

  • Dubai locations: Dubailand (Rukan, Bianca, Reportage Village, Taormina Village, R. Hills), Dubai Investment Park (Verdana) and Meydan Horizon (Verso and Époque)

  • Abu Dhabi locations: Masdar City, Al Raha Beach, Saadiyat Island, Al Reem Island and Yas Canal

  • Company's own figures: more than 116 projects, including 34 outside the UAE, and over 48,000 homes (August 2026); more than 122 projects launched and 51,000 homes (October 2026)

  • Sales, company-reported: AED 2.3 billion (2022), more than AED 3.7 billion (2023), about AED 5.7 billion (2024), AED 9.6 billion (2025)

  • Credit rating or listed shares: none found

Prices and availability change by phase, so ask our team for current figures.

Delivered in Dubai.

  • Rukan Tower, Wadi Al Safa, Dubailand: about 608 apartments in three connected towers, handed over in August 2024. A December 2020 report gave it a Q4 2022 delivery date (then about 488 units).

  • Rukan Lofts, Dubailand: first phase completed, developed with Continental Investment Company. Reportage's page describes the Rukan Lofts compound as more than 800 townhouses, with prices from AED 525,000 for units still on sale.

Delivered in Abu Dhabi.

  • Leonardo Residences, Masdar City: Reportage's first project, broke ground in April 2016 and handed over in 2019.

  • Oasis Residence 1 and 2, Masdar City: Oasis 1 handovers began in 2023 and Oasis 2 (about 304 units) in 2024.

  • Al Raha Lofts, Al Raha Beach: handovers had begun by August 2024.

Approaching handover. Verdana 1 in Dubai Investment Park, 305 four-bedroom townhouses on which construction started in 2022, shows 97.19% construction progress on Reportage's page. We found no handover announcement as of 11 November 2026. In September 2023 the company said it had delivered more than 3,000 units across Abu Dhabi and Dubai that year.

Progress figures are those on Reportage's project pages as read on 11 November 2026. The pages do not give handover dates except where stated.

  • Verdana, Dubai Investment Park: ten phases of townhouses and apartments, from studios to four bedrooms, from AED 465,000. Verdana 2 shows 54.40% progress. Later phases add 131 to 306 townhouses and 191 to 392 apartments each.

  • Bianca, Dubailand: 653 townhouses (507 two-bedroom, 56 three-bedroom, 90 four-bedroom) on about 112,000 sq m, launched in 2023; 54.5% complete; listed from AED 400,000.

  • Reportage Village, Dubailand: 1,767 two- to four-bedroom townhouses on land bought for AED 285 million in cash from Dubai Holding, launched in September 2023 at AED 1.55 million to AED 2.19 million. We found no official progress figure or handover date.

  • Taormina Village, Dubailand: 838 townhouses and villas, with three- to five-bedroom floor plans, from AED 3.3 million; 19.4% complete.

  • R. Hills, Dubailand: 902 two- to four-bedroom townhouses on 232,242 sq m, from AED 2.2 million, handover Q4 2028; construction listed as starting soon.

Ask for the latest DLD or escrow progress report for the exact phase, because the Verdana and Rukan names cover several separate projects with different dates.

Verso and Époque, Meydan Horizon. Announced on 2 October 2026, these are Reportage's first projects in Meydan, with 234 homes in all. Verso has 174 apartments (113 one-bedroom, 59 two-bedroom and two four-bedroom) over 15 upper floors with retail and 192 parking spaces. Époque has 60 one- and two-bedroom apartments over six upper floors. Amenities include pools, gyms, a padel court at Verso and lagoon-view promenades. Prices, payment plans and handover dates were not published in the launch release.

Abu Dhabi. Sensi on Saadiyat Island (89 homes, from AED 2.8 million) and Sila in Masdar City (101 townhouses, from AED 2.8 million) are on sale; Sila's page lists construction as starting soon, and Sensi's page shows no progress figure. The Wadi on Yas Canal, launched in September 2026 through Cosmo Developments, plans 3,950 apartments in an AED 6 billion project.

Announced but unnamed. Before the September 2026 International Property Show, Reportage said it was preparing three new developments in Meydan and Jumeirah Village Circle. Details had not been published by 11 November 2026.

What supports it. Reportage has finished several buildings in both emirates since 2019, including Rukan Tower, the first Rukan Lofts phase and three Masdar City buildings. Its reported sales have grown every year since 2022, and Verdana 1 is close to complete on the company's own figures.

What to weigh. Rukan Tower was handed over in August 2024 against a Q4 2022 date reported in 2020. A 2023 launch release said all projects were being built on schedule; we found no independent source to confirm that. The group is private, has no credit rating and does not publish audited accounts, so its debt-free description and sales figures cannot be checked from filings. It also sells many phases at once, which makes progress phase-specific.

Checks before buying. Confirm the project and phase are registered with RERA, that payments go to the escrow account named in the contract, the construction percentage on the latest escrow report, and the contractual handover date and any delay terms. Our off-plan buyer's guide covers these steps.

Reportage says it offers instalment plans on all its projects, but its project pages do not publish fixed terms, and terms change between phases. Ask for the payment schedule in writing and check that it matches the Sales and Purchase Agreement.

Buying in Dubai costs the Dubai Land Department transfer fee of 4% of the price plus admin fees. Off-plan sales are registered on Oqood. Purchases of at least AED 2 million can support a Golden Visa application, subject to DLD conditions; most Verdana and Bianca units sit below that level, while R. Hills and Taormina Village start above it.

Reportage builds in both emirates, and Abu Dhabi has its own rules on where foreigners can own. Our Dubai vs Abu Dhabi comparison explains the differences.

COMMON QUESTIONS

Frequently Asked Questions

It has a real delivery record but not a spotless one. Reportage has handed over Rukan Tower and the first Rukan Lofts phase in Dubai and several Masdar City buildings in Abu Dhabi. Rukan Tower, though, was handed over in August 2024 against a Q4 2022 date reported in 2020. Check the progress, escrow and contract dates of the exact phase you are buying.
There is no general answer, because the developer's name does not set the return. Reportage mainly sells lower-priced townhouses and apartments in Dubailand and Dubai Investment Park, where supply is large. Judge each unit on price per square foot, likely rent, service charges and handover risk.
Reportage is privately held. A September 2026 group release names Felix Limited as Reportage Group's main shareholder, and an August 2026 release describes Andrea Nucera as an owner and key founder. Its shares are not listed on any exchange.
Aref Al Khouri is chairman and Andrea Nucera is CEO and Managing Director. Simona Musso is Executive Director and Giovanni Nucera is International CEO, according to the company's website.
Reportage was founded in 2014 and is headquartered in Abu Dhabi. It also builds in Dubai and lists 19 countries on its website.
In August 2026 the company said it had more than 116 projects, 34 of them outside the UAE, with over 48,000 homes; by October 2026 it cited more than 122 projects launched and 51,000 homes. These are the company's own figures and include projects not yet built.
Rukan Tower in Wadi Al Safa, Dubailand, about 608 apartments in three connected towers handed over in August 2024, and the first phase of Rukan Lofts. Verdana 1 in Dubai Investment Park was 97.19% complete on the company's page on 11 November 2026.
Leonardo Residences in Masdar City, its first project, handed over in 2019, followed by Oasis Residence 1 and 2 in Masdar City and Al Raha Lofts on Al Raha Beach. Handovers at Oasis 2 and Al Raha Lofts had begun by August 2024.
The later Verdana phases in Dubai Investment Park, and Bianca, Reportage Village, Taormina Village and R. Hills in Dubailand. On 11 November 2026 Reportage's pages showed Bianca at 54.5%, Verdana 2 at 54.40% and Taormina Village at 19.4%.
Rukan Tower is the clearest public case. A December 2020 report gave it a Q4 2022 delivery date, and Reportage announced its handover in August 2024. We found no public announcement of handover dates for most current phases, so ask for the contractual date of the phase you buy.
Verdana is a multi-phase community of townhouses and apartments in Dubai Investment Park. The first phase has 305 four-bedroom townhouses, and Reportage lists ten phases, with prices from AED 465,000.
A Dubailand community of 1,767 two-, three- and four-bedroom townhouses, launched in September 2023 on land Reportage bought from Dubai Holding for AED 285 million in cash. Launch prices ran from AED 1.55 million to AED 2.19 million.
Bianca is a Dubailand townhouse community of 653 homes: 507 two-bedroom, 56 three-bedroom and 90 four-bedroom. It launched in 2023 and was 54.5% complete on Reportage's page on 11 November 2026.
R. Hills is a gated townhouse community in Dubailand with 902 homes of two to four bedrooms on 232,242 sq m. Reportage lists prices from AED 2.2 million and a Q4 2028 handover, with construction marked as starting soon.
They are Reportage's first projects in Meydan Horizon, announced on 2 October 2026. Verso has 174 apartments and Époque has 60, and both include pools, gyms and play areas. Prices and handover dates were not in the launch release.
Reportage offers instalment plans, but it does not publish fixed terms on its project pages and they vary by phase. Get the schedule in writing and check it against the Sales and Purchase Agreement before paying the booking amount.
For completed units such as Rukan Tower, a standard UAE mortgage is possible if you meet the bank's criteria. For off-plan phases, most buyers pay the developer's instalments and arrange a mortgage near handover, if the plan leaves a balance due then. Check with your bank before committing.
Yes, Reportage sells its Dubai projects to international buyers. Confirm the title type for the specific unit with the Dubai Land Department record before you sign.
The Dubai Land Department charges a 4% transfer fee plus admin fees. Off-plan purchases are registered on Oqood, and the developer's payment plan sets when instalments fall due.
Purchases of at least AED 2 million can support a Golden Visa application, subject to DLD conditions. Most Verdana and Bianca units are priced below that level, while R. Hills and Taormina Village start above it.
Reportage is private and focuses on lower-priced townhouses and apartments, while Emaar and Aldar are listed companies that publish audited results. That means less public financial information on Reportage. Compare the specific project, price and handover record rather than the brand.
Reportage reported sales of AED 9.6 billion for 2025. It reported about AED 5.7 billion in 2024 and more than AED 3.7 billion in 2023. These figures are company-reported, not audited.
It depends on the project. Verso's launch lists a padel court, gym, pool, yoga area and children's play areas, and Époque adds a lagoon-view promenade. Ask for the amenity plan and service charge estimate for the exact community.
Its website lists 19 countries, including Egypt, Saudi Arabia, Türkiye, Azerbaijan, Morocco, Rwanda, Uganda, Kenya, Albania and France. Its Egyptian projects include Montenapoleone in Mostakbal City, New Cairo.

Interested in Reportage Properties?

Speak to our experts and find your perfect Reportage Properties property.

View All Projects

FREE CONSULTATION

Get Expert Advice on
Reportage Properties Projects

Share your details and a dedicated advisor will personally guide you to the best Reportage Properties off-plan projects in Dubai.

Property Consultant
Need help?